Chapter 4 — Sequence of Operation
4-2
Part No. 750-184
A. GENERAL
Chapter 4 outlines the electrical sequencing of various controls through the
pre-purge, ignition, run, and shutdown cycles of the burner.
The program relay establishes the sequence of operation and directs the
operation of all other controls and components to provide an overall
operating sequence.
Notice
Note: The make or model of the program relay provided will
vary depending upon job specifications. The following
sequence applies regardless of the make or model. Please
refer to the Wiring Diagram (WD) prepared by Cleaver-
Brooks for your specific installation.
Abbreviations for the various electrical components are listed in Figure 4-1.
The sequences outlined in Chapter 4 employ specific nomenclature to aid in
applying the text to the wiring diagram.
The burner and control system are in starting condition when the following
conditions exist:
• Boiler water is up to the correct level, closing the low-water cutoff switch.
• The low-water light (panel) is off.
• The operating limit pressure control (steam boiler) or the operating limit
temperature control (hot water boiler) and high limit pressure or
temperature control are below their cutoff setting.
• All applicable limits are correct for burner operation.
• The load demand light glows.
All entrance switches are closed and power is present at the line terminals
of:
• Blower motor starter
• Air compressor motor starter (if provided)
• Oil heater relay (if provided)
• Oil pump motor starter (if provided).
The sequences do not attempt to correlate the action of the fuel supply
system or feedwater system except for the interlock controls that directly
relate to the action of the program relay. Chapters 6 and 7
contain operating
instructions and specific information on setting and adjusting the controls.
B. CIRCUIT AND INTERLOCK CONTROLS
The burner control circuit is a two-wire system designed for 115 Vac, 60 Hz,
single-phase power.
The electrical portion of the boiler is made up of individual circuits with
controls that are wired in a manner designed to provide a safe workable
sy stem . Th e program relay p rov id e s c o n n e c t i o n p oi n t s f o r t h e
interconnection of the various circuits.
The controls used vary depending upon the fuel oil or gas and the specific
requirement of applicable regulatory bodies. Refer to the boiler wiring
Summary of Contents for CB Ohio Special 100 HP
Page 2: ...ii ...
Page 8: ...viii ...
Page 42: ...Chapter 2 Burner Operation and Control 2 22 Part No 750 184 ...
Page 116: ...Chapter 6 Adjustment Procedures 6 28 Part No 750 184 ...
Page 126: ...Chapter 8 Inspection and Maintenance 8 6 Part No 750 184 ...
Page 153: ...Chapter 9 Parts Part No 750 184 9 3 Insulated Front Head Model CB LE ...
Page 154: ...Chapter 9 Parts 9 4 Part No 750 184 Insulated Front Head Interior Model CB LE ...
Page 155: ...Chapter 9 Parts Part No 750 184 9 5 Insulated Inner Door Model CB OS ...
Page 156: ...Chapter 9 Parts 9 6 Part No 750 184 Insulated Rear Head CB LE ...
Page 157: ...Chapter 9 Parts Part No 750 184 9 7 Insulated Rear Head CB LE ...
Page 158: ...Chapter 9 Parts 9 8 Part No 750 184 Insulated Rear Head CB OS ...
Page 159: ...Chapter 9 Parts Part No 750 184 9 9 Dry Oven Model CB LE ...
Page 161: ...Chapter 9 Parts Part No 750 184 9 11 Motor Impeller Model CB LE ...
Page 162: ...Chapter 9 Parts 9 12 Part No 750 184 Front Head Linkage ...
Page 170: ...Chapter 9 Parts 9 20 Part No 750 184 Control Cabinet Hawk ICS ...
Page 171: ...Chapter 9 Parts Part No 750 184 9 21 Control Panel Standard ...
Page 172: ...Chapter 9 Parts 9 22 Part No 750 184 Entrance Box ...
Page 173: ...Chapter 9 Parts Part No 750 184 9 23 Front Head Electrical CB LE ...
Page 174: ...Chapter 9 Parts 9 24 Part No 750 184 Front Head Electrical CB LE ...
Page 175: ...Chapter 9 Parts Part No 750 184 9 25 Front Head Electrical CB OS ...
Page 176: ...Chapter 9 Parts 9 26 Part No 750 184 Front Head Electrical CB OS ...
Page 179: ...Chapter 9 Parts Part No 750 184 9 29 Heavy Oil Piping 60 Steam CB LE ...
Page 180: ...Chapter 9 Parts 9 30 Part No 750 184 Heavy Oil Piping 60 Steam CB LE SEE TABLE NEXT PAGE ...
Page 181: ...Chapter 9 Parts Part No 750 184 9 31 Common Oil Parts Heavy Oil ...
Page 182: ...Chapter 9 Parts 9 32 Part No 750 184 Side Mounted Air Compressor Piping ...
Page 183: ...Chapter 9 Parts Part No 750 184 9 33 Air Compressor Piping CB OS ...
Page 185: ...Chapter 9 Parts Part No 750 184 9 35 Light Oil Piping ...
Page 186: ...Chapter 9 Parts 9 36 Part No 750 184 Light Oil Air Piping Front Head ...
Page 187: ...Chapter 9 Parts Part No 750 184 9 37 Light Oil Air Piping Front Head PAGE 9 31 ...
Page 191: ...Chapter 9 Parts Part No 750 184 9 41 Gas Train 125 150 HP ...
Page 193: ...Chapter 9 Parts Part No 750 184 9 43 Gas Train 200 HP ...
Page 195: ...Chapter 9 Parts Part No 750 184 9 45 Steam Pressure Controls ...
Page 196: ...Chapter 9 Parts 9 46 Part No 750 184 Hot Water Temperature Controls ...
Page 197: ...Chapter 9 Parts Part No 750 184 9 47 Water Column ...
Page 198: ...Chapter 9 Parts 9 48 Part No 750 184 Water Column ...
Page 199: ...Chapter 9 Parts Part No 750 184 9 49 Fireside Gaskets CB LE ...
Page 200: ...Chapter 9 Parts 9 50 Part No 750 184 Fireside Gaskets CB OS ...