Installing the Cabinet on a Concrete Pad
The cabinet is equipped with four lifting eyebolts. Attach slings to the eyebolts to lift and move the cabinet with a boom
crane or derrick. Position the boom crane or derrick truck near the installation site to perform this task.
The boom crane or derrick and lifting slings must be capable of lifting at least a 1000 lb. working load. Use wire rope slings
long enough to provide a minimum four foot vertical distance between the eyebolts and the sling junction to the boom line.
Use appropriately rated connecting links or lifting hooks.
Clearfield recommends using at least three people to install the cabinet: one to operate the crane or derrick, one to guide
the cabinet laterally as it lowers, and one to spot-check alignment of the mounting studs/holes and conduits/entry box as the
cabinet lowers.
DANGER!
The cabinet is very heavy. If it falls during lifting, it could cause serious injury or death to personnel.
Do not stand under the load or place any part of your body under the load during lifting. Follow local safety
practices for lifting and moving heavy loads.
CAUTION!
Installing the cabinet requires safe handling to ensure that no injury to personnel or damage to the
cabinet occurs.
Before installing the cabinet, verify that the splice compartment door is open to a locked position and that the battery
compartment door has been removed.
To install the cabinet on a concrete pad
Sweep the pad free of dirt and debris.
Install the isolation mat onto the concrete pad.
Check the four lifting eyebolts on the top of the cabinet to ensure that they are securely seated.
Attach the lifting slings to the boom line. Attach the other ends of the slings to the cabinet lifting eyebolts using
connecting links or hooks.
Lift the cabinet approximately 12 inches above the ground and position it directly above the foundation pad.
Slowly lower the cabinet onto the pad, keeping the mounting holes in the cabinet base aligned with the anchor
studs (or anchor holes) in the pad.