Step 7:
Step 8:
Step 9:
Step 10:
Step 11:
Note:
If properly aligned, the entry boxes in the splice compartment should slide down over the conduits pro
-
truding up from the pad as the cabinet lowers. If necessary, reach down through the entry boxes to grasp and
align the top of the conduit to guide it through the entry box. Do not reach under the cabinet.
Pull the earth ground wire into the splice compartment through the cable entry box.
After the cabinet rests on the pad, disconnect the slings from the cabinet lifting eyebolts.
Anchor the cabinet to the pad as follows:
• Pads with anchor studs:
a.
Get the four hex nuts, four square washers, and four lock washers from the installation kit.
b.
Install one square washer, lock washer, and hex nut onto each of the four anchor studs (two in the
splice compartment, two in the battery compartment).
c.
Tighten the hex nuts to secure the cabinet to the pad.
• Pre-cast pads with threaded inserts:
a.
Get four anchor bolts, four square washers, and four lock washers from the pre-cast pad kit.
b.
Install one square washer, lock washer, and anchor bolt into each of the four threaded mounting
inserts (two in the splice compartment, two in the battery compartment).
c.
Tighten the bolts to secure the cabinet to the pad.
Verify that all cabinet doors open and close freely. If necessary, use shims to level the cabinet.
Apply silicone caulking to the bottom perimeter of the cabinet.