Installing a Pre-Cast Pad
Transport the pre-cast pad to installation site.
Using a crane and slings, lift the pad into position above the gravel base inside the foundation hole.
Lower the pad onto the gravel base, allowing the conduits to pass through the cutout in the pad as
it descends.
Adjust the pad positioning on the gravel base until it is stable and level.
Pull the earth ground wire through the cutout in the pad, allowing at least four feet of wire to extend
above the top of the pad.
Backfill and grade around the pad perimeter with soil to secure the pad in place.
Verify that the pad remains level. Adjust as required.
Step 1:
Step 2:
Step 3:
Step 4:
Step 5:
Step 6:
Step 7:
Install the pre-cast pad according to the manufacturer’s instructions (typically supplied with the pad).
A general installation practice is described below for reference. Adapt the instructions as needed for local requirements,
practices, or conditions.
To install a pre-cast pad
WARNING!
The pre-cast concrete pad is extremely heavy. Handle with care to avoid personal injury or
damage to the pad.