Install the Shelf and FMECs
This chapter explains how to install the Cisco ONS 15454 SDH shelf assembly. For a summary of the
tools and equipment required for installation, see the
“Required Tools and Equipment” section on
.
Before You Begin
This section lists the chapter procedures (NTPs). Turn to a procedure for applicable tasks (DLPs). Read
the installation procedures and precautions before you install the ONS 15454 SDH and connect the
power source.
1.
NTP-D1 Unpack and Inspect the ONS 15454 SDH Shelf Assembly, page 1-4
—Complete this
procedure before continuing with the
“NTP-D2 Install the Shelf Assembly” procedure on page 1-5
2.
NTP-D2 Install the Shelf Assembly, page 1-5
—Complete this procedure to install the shelf
assembly in a rack.
3.
NTP-D3 Open and Remove the Front Door, page 1-6
—Complete this procedure to access the
equipment before continuing with other procedures in this chapter.
4.
NTP-D219 Open and Remove the FMEC Cover, page 1-7
—Complete this procedure to access the
electrical facility connection assembly (EFCA) for the front mount electrical connections (FMECs)
before continuing with other procedures in this chapter.
5.
NTP-D220 Install the Power and Signal FMECs, page 1-7
—Complete this procedure if you plan to
install electrical cards. This procedure is a prerequisite to the
“NTP-D224 Install the Electrical Card
Cables on the FMECs” procedure on page 1-16
.
6.
NTP-D6 Install the Power and Ground, page 1-10
—Complete this procedure before continuing with
the
“NTP-D7 Install the Fan-Tray Assembly” procedure on page 1-11
.
7.
NTP-D7 Install the Fan-Tray Assembly, page 1-11
—Complete this procedure to install the fan-tray
assembly in the shelf.
8.
NTP-D222 Install the E1-75/120 Conversion Panel, page 1-13
—Complete this procedure if you use
the E1-42 card and plan to use 75-ohm unbalanced interfaces.
9.
NTP-D223 Attach Wires to Alarm, Timing, LAN, and Craft Pin Connections, page 1-15
—Complete
as needed to set up wire-wrap pin connections and craft connections.
10.
NTP-D224 Install the Electrical Card Cables on the FMECs, page 1-16
—Complete this procedure
if you will install electrical cards.
11.
NTP-D10 Route Electrical Cables, page 1-16
—Complete as needed.
Summary of Contents for ONS 15454 SDH
Page 26: ...Tables vi Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 ...
Page 62: ...xxii Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 About this Guide ...
Page 64: ...xxiv Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 About this Guide ...
Page 66: ...xxvi Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 About this Guide ...
Page 860: ...Index IN 28 Cisco ONS 15454 SDH Procedure Guide R6 0 78 17194 01 ...