CHAPTER 3. EQUIPMENT ROOM DESIGN
1-pair patch cords/jumper wires are then run from the purple terminal
block rows to the green terminal block rows in order to establish the
correct 3-pair modularity. Table 3-H shows switch port appearances at
the cross-connect field. Figures 3-53, 3-54, and 3-55 show the carrier
connectors on the rear of the switch that connect to the purple field.
CABINET
FANS
CONTROL CARRIER A
PORT CARRIER B
REAR VIEW
A10
A01
B20
B11
B10
B01
Figure 3-53. System 75, Slot Addresses for 2-Carrier Cabinet
3-78
Summary of Contents for System 75
Page 1: ...AT T AT T System 75 and System 75 XE Wiring...
Page 2: ...AT T AT T System 75 and System 75 XE Wiring 555 200 111 Issue 2 August 1989...
Page 16: ...System Wiring Figure 1 2 System Uniform Wiring Plan 1 7...
Page 17: ...CHAPTER 1 INTRODUCTION Figure 1 3 Sample Uniform Wiring Installation 1 8...
Page 29: ...CHAPTER 2 HARDWARE 66 110 Type Figure 2 1 Block Diagram of System 75 or 75 XE Installation 2 2...
Page 35: ...CHAPTER 2 HARDWARE 66 110 Type Figure 2 4 110A Type 100 Pair Terminal Block 2 8...
Page 36: ...110 Type Hardware Description Figure 2 5 110A Type 300 Pair Terminal Block 2 9...
Page 98: ...Typical System Equipment Room Floor Plans 3 15...
Page 143: ...CHAPTER 3 EQUIPMENT ROOM DESIGN 3 60...
Page 144: ...Equipment Room Hardware And Cabling Installation 3 61...
Page 162: ...Equipment Room Hardware And Cabling Installation 3 79...
Page 163: ...Equipment Room Hardware And Cabling Installation 3 80...
Page 197: ...Tables Table 4 A Recommended Protectors 4 42 v...
Page 212: ...Adjunct Powering 4 15...
Page 214: ...Adjunct Powering 4 17...
Page 216: ...Patch Cord Jumper Installation And Administration 4 19...
Page 241: ...CHAPTER 4 STATION WIRING 4 44...
Page 244: ...Miscellaneous Wiring Installation 4 47...
Page 246: ...Miscellaneous Wiring Installation 4 49...
Page 252: ...Miscellaneous Wiring Installation 4 55...
Page 254: ...Miscellaneous Wiring Installation 4 57...
Page 314: ...CHAPTER 5 AUXILIARY EQUIPMENT INSTALLATION 5 41...
Page 324: ...CHAPTER 5 AUXILIARY EQUIPMENT INSTALLATION 5 51...