07 COMMISSIONING
7) Wiring across shipping splits is completed according to the
instructions in this user manual (3BHS842007 E01 Rev C).
□
8) Ground cable of the drive is securely connected at both ends.
□
9) Cable armor and screens of power supply cables are connected
to PE ground busbar.
□
10) The transformer and motor cables are installed but the
conductors not connected at both ends (cables and drive must
be insulation resistance tested, ie, Megger test,
before connection).
□
7.6.3
Main circuit breaker (MCB)
1) MCB selected as per “Main circuit breaker specification”
(1)
□
2) High-voltage power connections completed
□
3) MCB is ready to be tested with drive
□
4) MCB protection relay settings are tested
□
5) Protection devices (eg, door locks) are tested and in operation.
□
6) Local operation of MCB is disabled.
□
7) Emergency-off loop is tested.
□
(1)
Pay attention to MCB opening time and installation of undervoltage coil or second
opening coil
7.6.4
Input transformer checklist
1) Grounding is completed
□
2) Transformer auxiliaries (eg, dehydrating breathers, cooling,
protection devices) are ready.
□
3) Protection devices are tested and in operation.
□
7.6.2
Electrical installation checklist (continued)