9. MAINTENANCE
Removing the Capsule Assembly
IMPORTANT
Exercise care as follows when cleaning the
capsule assembly.
• Handle the capsule assembly with care, and be
especially careful not to damage or distort the
diaphragms that contact the process fluid.
• Do not use a chlorinated or acidic solution for
cleaning.
• Rinse thoroughly with clean water after clean-
ing.
1) Remove the CPU assembly as shown in Subsection
9.4.2.
2) Remove the two Allen screws that connect the
transmitter section and pressure-detector section.
3) Separate the transmitter section and pressure-
detector section.
4) Remove the nuts from the four flange bolts.
5) Hold the capsule assembly by hand and remove the
cover flange.
6) Remove the capsule assembly.
7) Clean the capsule assembly or replace with a new
one.
Reassembling the Capsule Assembly
1) Insert the capsule assembly between the flange
bolts, paying close attention to the relative positions
of the H (high pressure side) and L (low pressure
side) marks on the capsule assembly.
Replace the two capsule gaskets with new gaskets.
2) Install the cover flange on the high pressure side,
and use a torque wrench to tighten the four nuts
uniformly to a torque shown below.
Model
EJA110A
EJA120A
EJA130A
Torque(N·m)
39{4}
147
{kgf·m}
{15}
3) After the pressure-detector section has been reas-
sembled, a leak test must be performed to verify
that there are no pressure leaks.
4) Reattach the transmitter section to the pressure-
detector section.
5) Tighten the two Allen screws. (Tighten the screws
to a torque of 5 N·m)
6) Install the CPU assembly according to Subsection
9.4.2.
7) After completing reassembly, adjust the zero point
and recheck the parameters.
F0904.EPS
Transmitter section
Pressure-detector section
Cover flange
Capsule gasket
Flange bolt
Allen screw
Nut
Figure 9.4.2 Removing and Mounting the Pressure-
detector Section
9.4.4 Replacing the Process Connector
Gaskets
This subsection describes process connector gasket
replacement. (See Figure 9.4.3.)
(a) Loosen the two bolts, and remove the process
connectors.
(b) Replace the process connector gaskets.
(c) Remount the process connectors. Tighten the bolts
securely and uniformly to a torque of 39 to 49 N·m
{4 to 5 kgf·m}, and verify that there are no pressure
leaks.
F0905.EPS
Bolt
Process connector
Process connector gasket
Figure 9.4.3 Removing and Mounting the Process
Connector