1.
At the cooling unit, verify that it is the lead unit of the group:
•
Touch
, then
>
BMS & Teamwork Setup
>
U2U Setup
.
•
In the CONTROL BOARD column, verify that the
U2U Address
is 1.
If it is the lead unit, continue with step
.
If it is not the lead unit, find the lead unit and start at step
.
2.
Touch
, then
>
BMS & Teamwork Setup
>
Teamwork / Standby
. The TEAMWORK/STANDBY panel
opens.
3.
Touch
Unit Rotation
. The UNIT ROTATION CONTROL panel displays.
4. Touch
Rotate Now
, then touch
Save
. The operating and standby units are rotated.
Vertiv™ | Liebert® iCOM™ Installer/User Guide
70
Содержание Liebert iCOM DP400/500
Страница 8: ...Vertiv Liebert iCOM Installer User Guide vi This page intentionally left blank...
Страница 64: ...Vertiv Liebert iCOM Installer User Guide 56 This page intentionally left blank...
Страница 70: ...Vertiv Liebert iCOM Installer User Guide 62 This page intentionally left blank...
Страница 86: ...Vertiv Liebert iCOM Installer User Guide 78 This page intentionally left blank...
Страница 90: ...Vertiv Liebert iCOM Installer User Guide 82 This page intentionally left blank...
Страница 110: ...Vertiv Liebert iCOM Installer User Guide 102 This page intentionally left blank...
Страница 140: ...Vertiv Liebert iCOM Installer User Guide 132 This page intentionally left blank...
Страница 178: ...Vertiv Liebert iCOM Installer User Guide 170 This page intentionally left blank...
Страница 179: ...Vertiv Liebert iCOM Installer User Guide...