M3000
Installation Manual
8
Getting started roadmap
The following is a basic outline for installing and setting up your M3000 system. Some steps may have been
done for you depending on what you ordered. Some steps are optional, depending on the additional equipment
you plan to use. These steps are noted.
1. Determine the cable clamps needed and obtain them prior to starting the installation.
During the installation, remember to:
•
Label all connections/cables for ease of maintenance.
•
Leave enough slack in the wiring so the cables can be “dressed.” This minimizes interference
during board removal or replacement.
2. Unpack your system. See
Product overview
on page 2.
3. Mount the enclosure. See
Mounting
on page 11.
4. Connect AC power to the power supply. See
Connecting the AC input power to the M3000
on page 19.
5. Mount and install the battery backup. See
Installing the battery backup, AC fail, and low battery
on
page 22.
6. Wire up the Power/Communications board. Be sure to configure and verify the switch settings. Refer
to
Chapter 3,
Power/Communications board
on page 17.
7. If using networked controllers, verify that your network is up and running.
8. Install and wire up the PXNplus CPU board. Be sure to configure and verify the jumpers. If this is a
network controller, plug in the network cable. Refer to
Chapter 4,
PXNplus CPU board
on page 35.
9. Install the reader board(s) into the enclosure and wire up the readers to the controller. Be sure to
configure and verify the switch settings, jumpers, and/or resistor packs. Refer to
Chapter 5,
Reader
processing boards
on page 45.
10. If using digital inputs (DIs), insert the DI board into the enclosure and wire the DIs to the board. Be
sure to configure and verify the switch settings. See
20DI board
on page 86.
11. If using digital outputs (DOs), insert the DO board into the enclosure and wire the DOs to the board.
Be sure to configure and verify the switch settings. See
16DO and 16DOR boards
on page 90.
12. Test the wiring before you apply power. Refer to
Testing
on page 96.
13. Configure your controller using the Integrated Configuration Tool. Refer to
Chapter 8,
Controller
firmware tools
on page 97.
CAUTION:
Do not apply power to any component until the installation is complete. Damage to components may
occur if power is incorrectly applied.
Содержание M3000
Страница 1: ...M3000 Installation Manual P N 460630001H 15JUNE11 ...
Страница 10: ...M3000 Installation Manual x ...
Страница 37: ...Chapter 3 Power Communications board 27 Host computer wiring Figure 9 Wiring host computer to first M3000 ...
Страница 39: ...Chapter 3 Power Communications board 29 Figure 11 Wiring modem to M3000 M 5 or serial printer ...
Страница 41: ...Chapter 3 Power Communications board 31 Figure 13 Wiring downstream away from the host using RS 232 ...
Страница 47: ...Chapter 4 PXNplus CPU board 37 Board layout Figure 16 PXNplus CPU board layout ...
Страница 58: ...M3000 Installation Manual 48 Board layout Figure 17 2RP reader board layout ...
Страница 65: ...Chapter 5 Reader processing boards 55 Figure 21 Wiring 2RP to Wiegand Strobed F 2F and supervised F 2F readers ...
Страница 68: ...M3000 Installation Manual 58 Figure 24 Wiring 2RP door strike external relay ...
Страница 72: ...M3000 Installation Manual 62 Board layout Figure 27 2SRP supervised reader board layout ...
Страница 78: ...M3000 Installation Manual 68 Figure 30 Wiring 2SRP to Wiegand F 2F Strobed and Supervised F 2F Readers ...
Страница 82: ...M3000 Installation Manual 72 Figure 19 Wiring 2SRP door alarm contact and exit request ...
Страница 84: ...M3000 Installation Manual 74 Figure 21 Wiring 2SRP door strike external relay ...
Страница 89: ...Chapter 5 Reader processing boards 79 Board layout Figure 24 8RP reader board layout ...
Страница 92: ...M3000 Installation Manual 82 Figure 26 Wiring 8RP to F 2F or Supervised F 2F Readers ...
Страница 94: ...M3000 Installation Manual 84 ...
Страница 97: ...Chapter 6 Optional DI and DO boards 87 Figure 31 20DI board layout ...
Страница 99: ...Chapter 6 Optional DI and DO boards 89 Figure 32 Wiring DI point ...
Страница 101: ...Chapter 6 Optional DI and DO boards 91 Figure 33 16DO board layout ...
Страница 102: ...M3000 Installation Manual 92 Figure 34 16DOR board layout ...
Страница 104: ...M3000 Installation Manual 94 Figure 36 Wiring output device to 16DOR board ...
Страница 152: ...M3000 Installation Manual 142 ...
Страница 156: ...M5 controller Installation Manual 146 Figure 76 Installing ferrite ...
Страница 160: ...M5 controller Installation Manual 150 ...
Страница 172: ...M3000 Installation Manual 162 ...