Chapter 3
Installing a Tape Library Tower Version
3-7
2. Press the power switch to the on position.
When you power on the tape library, the following events occur:
■
Cooling fan begins to rotate.
■
Main Screen appears on the LCD.
■
Tape drives perform their initiation tests.
■
Tape library performs a 40-second, initiation test.
During this test, the tape library first engages the locking solenoid in the front door,
then the CHM does the following tests:
■
Verifies its full range of motion by moving along the long axis
■
Verifies the presence of the cartridge holder by touching it
■
Reseats all cartridges by touching each of them
■
Moves to the park position
If the tape library does not power on as described, check the following:
■
If the LCD is not illuminated:
■
Is the power switch in the on position?
■
Is the power cord inserted correctly?
■
Is the fuse good?
■
If the LCD is illuminated:
■
Is there an error message or error code on the LCD?
■
Is the door closed and locked?
3.7
Setting SCSI IDs
If you determined that you need to change one or more of the tape library’s default
SCSI ID settings (2, 4, and 5), then perform the steps in Section 7.3.1, “Set SCSI IDs,”
on page 7-6.
Содержание StorEdge L400
Страница 24: ...xxiv Sun StorEdge L400 Installation and User s Guide April 1998 ...
Страница 30: ...1 6 Sun StorEdge L400 Installation and User s Guide April 1998 ...
Страница 86: ...6 14 Sun StorEdge L400 Installation and User s Guide April 1998 ...
Страница 140: ...C 6 Sun StorEdge L400 Installation and User s Guide April 1998 ...
Страница 162: ...Index 6 Sun StorEdge L400 Installation and User s Guide April 1998 ...