D3 Moving by Crane
Preparations
Components
41
Foldable Cover (multi-layer
plywood sheeting)
44
Climbing Shoe RCS
85
Guardrails
Assembly
1. Mount the top Slab and Climbing
Shoes (44a) on the next floor slab.
Open guiding skids on the top Climb-
ing Shoe (44a), deactivate the climb-
ing pawl.
2. Activate climbing pawls on the mid-
dle Slab Shoe (44b). The load is still
carried on the bottom Slab Shoe
(44c).
3. Remove temporary connections be-
tween the Climbing Units.
4. Dismantle formwork in the area of
the slab edge.
5. Mount trailing guardrails (85).
6. Fold up Foldable Covers (41) and se-
cure.
7. From a safe position, attach crane
lifting gear to Crane Eye BR-2 2.5 t.
8. Leave climbing enclosure and area of
risk.
(Fig. D3.01)
For operating the Climbing Shoes, see
Section "Opening and Closing the
Climbing Shoe" on Page 120 as well as
Section "Activating and Deactivating
the Climbing Pawl" on Page 122.
Fig. D3.01
RCS P Climbing Protection Panel
Instructions for Assembly and Use – Standard Configuration
Содержание RCS P
Страница 13: ...13 RCS P Climbing Protection Panel Instructions for Assembly and Use Standard Configuration...
Страница 93: ...93 RCS P Climbing Protection Panel Instructions for Assembly and Use Standard Configuration...
Страница 101: ...101 RCS P Climbing Protection Panel Instructions for Assembly and Use Standard Configuration...
Страница 169: ...169...