12
Store and transport components ensur-
ing that no unintentional change in their
position is possible. Detach lifting ac-
cessories and slings from the lowered
components only if they are in a stable
position and no unintentional change is
possible.
Do not drop the components.
Use PERI lifting accessories and slings
and only those load-bearing points pro-
vided on the component.
During the moving procedure
ensure that components are picked
up and set down so that unintention-
al falling over, falling apart, sliding,
falling down or rolling is avoided.
no persons are allowed to remain
under the suspended load.
The access areas on the construction
site must be free of obstacles and
tripping hazards, as well as being
slip-resistant.
For transportation, the surface used
must have sufficient load-bearing
capacity.
Use original PERI storage and transport
systems, e.g. crate pallets, pallets or
stacking devices.
Storage and Transportation
Climbing procedure
The climbing enclosure cannot be
mounted for the next concreting step
until the required concrete strength has
been achieved.
As a result of the moving procedure,
unprotected leading edges are formed.
Such affected areas are to be cordoned
off and additional equipment must be
in place to secure those persons work-
ing at the falling edge, e.g. personal
protective equipment against falling
from a height (PPE)!
Site personnel, construction materials
or tools may not be transported with
the crane during moving operations.
Exceptions to this can be determined
through the operational working and
assembly instructions on the basis of a
corresponding risk assessment.
The climbing procedure must be
monitored by a competent and
qualified person.
During the climbing procedure, clamp-
ing and crushing hazards are present
that result from moving components.
Those persons carrying out the climb-
ing procedure must be fully informed
about all possible hazards.
All persons who are not required to
carry out the climbing procedure must
leave the area of risk.
When climbing with the hydraulic
climbing device, specifications regard-
ing the arrangement of the hydraulic
hoses are to be observed. If the stand-
ard arrangement is not possible, an au-
thorised person must determine a safe
and secure alternative.
In case of a malfunction, lower the
platform to the next possible position,
leave the climbing unit in a safe and
secure manner and notify an author-
ised person immediately!
Safety Instructions
RCS P Climbing Protection Panel
Instructions for Assembly and Use – Standard Configuration
Содержание RCS P
Страница 13: ...13 RCS P Climbing Protection Panel Instructions for Assembly and Use Standard Configuration...
Страница 93: ...93 RCS P Climbing Protection Panel Instructions for Assembly and Use Standard Configuration...
Страница 101: ...101 RCS P Climbing Protection Panel Instructions for Assembly and Use Standard Configuration...
Страница 169: ...169...