C4 Suspension on the Structure
Troubleshooting
Warning
During assembly on the construction
site, components may fall to the
ground and hit people below. This
could lead to serious injuries or even
death.
⇒
Cordon off areas of risk under the
working areas.
Problem
Cause
Measures
Guiding skids cannot be closed.
– Climbing Rail is not completely in
the right position in the Guide Shoe.
– Pull Climbing Rail inwards with the
Guide-in Tool.
– Climbing rail spacing not correct.
– Detach climbing enclosure and adjust
spacing of Climbing Rail.
– Slab Shoe spacing is not correct.
– Slightly loosen the leading Anchor
Bolt, close the guiding skids and
tighten them using component toler-
ances.
Alternatively:
– Mount new anchoring through the
slab with tie rods and wingnut coun-
terplates.
Climbing Unit does not lie on the
planned Spacers on both sides.
– Climbing Rail rests on a Slab Shoe
that is positioned below.
– Floor height is approx. a multiple of
50 cm.
– Raise the Climbing Unit by approx.
10 cm using the crane. Deactivate
the pawls of all Slab Shoes posi-
tioned above. Position Climbing Unit
with the planned Spacer on the pawl
of the bottom Slab Shoe.
RCS P Climbing Protection Panel
Instructions for Assembly and Use – Standard Configuration
Содержание RCS P
Страница 13: ...13 RCS P Climbing Protection Panel Instructions for Assembly and Use Standard Configuration...
Страница 93: ...93 RCS P Climbing Protection Panel Instructions for Assembly and Use Standard Configuration...
Страница 101: ...101 RCS P Climbing Protection Panel Instructions for Assembly and Use Standard Configuration...
Страница 169: ...169...