Installation Manual
Starting the System -- Off-Grid (Black Start)
Note:
the batteries will always start. The status indicator must be
pressed to determine whether or not the batteries are in a state to be
charged. Batteries must be above 0-10% state of charge (SoC) (blinking
red) to be charged. If the batteries are blinking red, they may not charge
on the inverter, you will then need an external power supply.
Note:
the system will black start from PV automatically once there is
enough solar power and battery SoC.
Note:
the system will almost always manually “black start” the system
from batteries but may not maintain (system shutdown right away) if the
batteries SoC is not high enough. In that case, 1) reduce the essential
load or 2) wait for either the grid voltage to return or for enough solar
power and battery SoC to operate the essential loads again.
Operation and Display Panel
1. Check that cables are properly connected,
2. Turn ON External Solar by disabling Solar PV Rapid Shutdown (If
installed)
3. Turn ON: (a) AC Grid Breaker, (b) Battery Breaker, (c) (DC Coupled
only) PV Solar Switch
4. Turn ON the Main Switch (located on the left side of the inverter).
5. If the inverter has PV or GRID input, then the system will
automatically start. If only battery starts the inverter, press the Enter
button for five seconds until two beeps are heard. The system will
boot up in under sixty seconds.
6. Check output voltage: L1-L2 240 VAC; L1-N 120 VAC and L2-N 120
VAC.
7. Turn ON LOAD Breaker.
Содержание EverVolt EVAC-105-6
Страница 1: ...V 01012021 Installation Service Manual FOR AC AND DC COUPLED EVERVOLT SYSTEMS ...
Страница 65: ...65 Installation Manual Operation and Display Panel ...
Страница 76: ...76 Installation Manual Configuring the Hardware PV INPUT IS ONLY USED FOR EVERVOLT DC COUPLED SYSTEM ...
Страница 83: ...83 Installation Manual Step 5 Install the Generator wire ...