OPERATIONAL TESTING (Continued)
SmartHub Activation:
Step 1: Verify system is turned on from the previous section "To Startup
Equipment."
Step 2: make sure the SmartHub has three connections:
a. Power, 5 VDC plug into the essential loads
b. Communication cable, SmartHub RS485 to Inverter RS-485 S
c. Ethernet cable from your internet source to the SmartHub, or
wifi connection.
Step 3: Confirm indicators are blinking on SmartHub USB.
Step 4: Confirm Inverter Main Screen shows connection to SmartHub.
See images below.
Operational Testing
Indicates the connection the the SmartHub