IG-308-EN version 01; 03/06/2022
35
General instructions
cgm
.3-huv system: Fully gas-insulated
medium-voltage switchgear
Recommended sequence of operations
5.4.3. Opening operation from earthing position
1.
Move the actuating shaft access handle in the yellow
zone to its bottom position.
2. Opening operation:
Insert the lever in the earthing switch actuating shaft,
move the actuating arm to the end and turn anti-
clockwise 90º.
Figure 5.10.
Lever turn process
3.
Verify that the cubicle is in isolating position.
Figure 5.11.
Earthing switch opened