General instructions
cgm
.3-huv system: Fully gas-insulated
medium-voltage switchgear
Recommended sequence of operations
Side incoming earthing operation
Initial conditions: circuit-breaker closed and earthing switch
S1 and S2 open.
Access to the side incoming earthing is linked to the
different positions of the elements connected to the
-huv function (circuit-breakers open).
1.
Open the circuit-breaker by pressing the "O" button on
the front keypad and check the status indicating relay.
Figure 5.56.
Opening button detail
2.
Select using the lever or check the position of the
selector handle in position S1.
Figure 5.57.
Selector handle detail