IG-308-EN version 01; 03/06/2022
22
Installation
General instructions
cgm
.3-huv system: Fully gas-insulated
medium-voltage switchgear
2.
Remove the cable compartment cover, using the central
handle on the cover to pull it up and forward.
3.
Anchor the cubicle to the floor of the facility using
M10 bolts in the points prepared in its base. This will
prevent displacements or vibrations due to causes such
as short-circuiting, flooding, etc. The following levels
and figures should be taken into account:
Figure 4.7.
Removing the cable compartment cover
Anchoring dimensions [mm]
Module
a
b
c
d
e
f
g
Internal arc 1 s
l
50
368
245
-
-
540
-
v
50
545
325
-
-
-
rbv
50
533
245
-
-
-
ma
36
525
-
-
-
-
rc
50
325
340
-
-
-
125
lv
50
533
245
-
-
-
Table 4.5.
Anchoring dimensions