IG-308-EN version 01; 03/06/2022
44
Recommended sequence of operations
General instructions
cgm
.3-huv system: Fully gas-insulated
medium-voltage switchgear
3. Switch-disconnector closing operation:
a. Manual operation
.
Insert the lever in the switch-disconnector actuating
shaft, move the actuating arm to the end and turn
clockwise.
b. Motorised operation
(BM driving mechanisms).
Activate the corresponding operation command.
Figure 5.26.
Lever turn detail
4.
Remove the lever. The handle returns to its original
position.
5.
For manual driving mechanisms, charge the springs
by introducing the spring charging lever in the spring
charge shaft (k) and turn until the charged spring
indicating relay changes status.
For motorised driving mechanisms (AMV):
Close the
circuit-breaker by pressing the close button.
6.
Close the circuit-breaker by pressing the "l" button and
check the status indicating relay.
Figure 5.27.
Closing button detail