Procedure
Step 1 Determine the installation position of the server and check whether floating nuts
are installed. If not, install them first.
Figure 3-91 Installing a floating nut
Step 2 Lift the server. This task requires at least two people.
Step 3 Place the server on the guide rails and push it in to the cabinet.
Step 4 When the two mounting ears on the server contact the mounting bars on the
rack, tighten the captive screws on the mounting ears to secure the server.
Figure 3-92 Installing a TaiShan 200 server
Step 5 Connect the power cable to the TaiShan 200 server.
1. Wear an ESD wrist strap or ESD gloves.
2. Connect one end of the power cable to the cable port on the AC power
module of the server.
FusionModule2000-S Smart Modular Data Center
User Manual
3 Hardware Installation
Issue 03 (2021-07-15)
Copyright © Huawei Technologies Co., Ltd.
81