Application Scenario Screw Specifications
Torque (Kgf·cm)
(Tolerance: ±10%)
M5
25–30
M6
32–37
7.5 Installation Verification
Cabinet Installation Checklist
No.
Check Item
Check Result
1
The cabinets are placed according to the
equipment room layout diagram.
□ Passed □ Failed
2
The height deviation of all cabinets and the depth
deviation of adjacent cabinets are less than 5 mm.
□ Passed □ Failed
3
All bolts and screws are firmly tightened,
especially on electrical connections. Flat and
spring washers are used with each bolt, and
spring washers are placed on the top of flat
washers.
□ Passed □ Failed
4
The cabinets are clean and meet dustproof
requirements.
□ Passed □ Failed
5
The paint on the cabinet exterior is intact. If paint
flakes off, repaint that area immediately to avoid
corrosion.
□ Passed □ Failed
6
The cabinet doors and locks work properly.
□ Passed □ Failed
7
All labels are correct, clear, and complete.
□ Passed □ Failed
8
There is no foreign matter such as adhesive tape,
cable ties, paper, or packing materials left around
the cabinets.
□ Passed □ Failed
9
The cabinet filler panels are adjusted to ensure
that the cold aisle and hot aisle are isolated.
□ Passed □ Failed
Aisle Containment Installation Checklist
No.
Check Item
Check Result
1
All components of the aisle containment are
installed.
□ Passed □ Failed
2
All labels are correct, clear, and complete.
□ Passed □ Failed