Figure 5-59 Server Recording Plan
4. Click Save.
----End
5.3.13 Linkage Control
Prerequisites
●
You have obtained the IP address of the ECC800-Pro as well as the user name
and password used for WebUI login.
●
A PC with an IP address in the same network segment as that of the ECC800-
Pro is prepared, and the PC has connected to port WAN1 on the ECC800-Pro.
●
Enable linkage control function is set to Yes.
Commissioning Procedure
Step 1 Choose Home > Plan View, click Create smart module, and set Layout, Half-size
cabinet qty./row, and Room monitoring based on the actual smart module
scenario.
NO TE
● Cold and hot aisle containment scenario: Set the Layout to Single-row dual aisle and
the Aisle containment type to Cold.
● Hot aisle containment scenario: Set the Layout to Single-row narrow aisle 2 and the
Aisle containment type to Hot.
The cold and hot aisle containment is used as an example in the following figure.
FusionModule2000-S Smart Modular Data Center
User Manual
5 Power-On Commissioning
Issue 03 (2021-07-15)
Copyright © Huawei Technologies Co., Ltd.
206