NO TICE
● Only one cable can be connected to a wiring terminal of the general input unit.
● You are advised to install cables from the bottom up.
● If the input MCCB current level is 250 A, the No. 1 screw is M10 and the No. 2
screw is M12. If the input MCCB current level is 400 A, both the No. 1 and No. 2
screws are M12.
Figure 4-10 Installing input power cables
Step 3 If there is any gap around the rubber rings of the cables after the installation, seal
it from the inside using sealing putty.
Step 4 Reinstall the cover of the general input unit.
Figure 4-11 Installing the cover of the general input unit
Step 5 Install load cables.
1. Remove the protective cover from the load wiring port.
2. Remove the ring buckle.
3. Press the front part of the round connector backwards and insert the
connector into the load wiring port.
4. Check the insertion depth of the round connector. Ensure that the red line is
not visible.
5. Reinstall the ring buckle.
FusionModule2000-S Smart Modular Data Center
User Manual
4 System Cabling
Issue 03 (2021-07-15)
Copyright © Huawei Technologies Co., Ltd.
109