No.
Check Item
Check Result
3
Power cables and ground cables are not coiled
and excess parts are cut off.
□ Passed □ Failed
4
Lugs for power cables and ground cables are
welded or crimped securely.
□ Passed □ Failed
5
Power cables and ground cables are routed and
bound separately from other cables.
□ Passed □ Failed
11
DIP switches on devices are correctly set.
□ Passed □ Failed
Customer signature:
Check date:
7.6 Acronyms and Abbreviations
A
AC
alternating current
ATS
automatic transfer switch
B
BCB
battery circuit breaker
BIB
battery control I/O board
BIM
battery interface module
BSPP
British Standard Pipe
Parallel Thread
BSPT
British Standard Taper
Pipe Thread
D
DC
direct current
FusionModule2000-S Smart Modular Data Center
User Manual
7 Appendix
Issue 03 (2021-07-15)
Copyright © Huawei Technologies Co., Ltd.
276