7.1.5 (Optional) Setting Parameters for the BCB Box
Prerequisites
A BCB box is installed.
Procedure
Step 1 Choose System Info > Settings > Dry Contact Set, set MUE05A connection to
Enable, and set BCB connection [OL] and Battery breaker [STA] to Enable.
Figure 7-3 BCB connection settings
----End
7.1.6 (Optional) Configuring the Bottom Cabling Cabinet
Prerequisites
The bottom cabling cabinet has been deployed.
Procedure
Step 1 On the LCD, choose System Info > Settings > System Settings and set Bottom
cable entry cabinet to Enable.
----End
7.1.7 (Optional) Setting the Backfeed Protection Card
Prerequisites
A backfeed protection card is installed.
Procedure
Step 1 On the LCD, choose System Info > Settings > Dry Contact Set and set MUE06A
connection to Enable.
UPS5000-H-(400 kVA-800 kVA)
User Manual (100 kVA Power Module)
7 Single UPS Commissioning
Issue 02 (2021-04-22)
Copyright © Huawei Technologies Co., Ltd.
111