Table 6-2
Setting generator parameters
Main Menu
Second-Level
Menu
Default Value
Setting
System
Configuration
Generator Usage
No Generator
No Generator
or
Generator In Use
----End
6.2 Power-On Commissioning for the Power Supply and
Distribution System
Prerequisites
The installation has been checked.
Configure an upstream protective device that meets the overload and short-circuit protection
requirements for the Converged Cabinet. If one power input is overloaded or short-circuited,
the system can switch to the other power input automatically.
Context
shows the circuit breakers on the front panel of the Converged Cabinet.
The power distribution subrack of the Converged Cabinet can be the ATS PDU, 6 U PDU, or 3 U PDU.
This section describes the positions of circuit breakers in the Converged Cabinet when the Converged
Cabinet is configured with both the ATS PDU and 6 U PDU.