FusionModule800 Smart Small Data Center
Installation Guide (Six Fans)
6 Power-On Commissioning
Issue 10 (2019-12-20)
Copyright © Huawei Technologies Co., Ltd.
242
Table 6-6
Commissioning the sensor
Check Method
Normal Connection Status
Alarm Clearance Method
Simulate a smoky
environment under
the smoke detector.
Smoke DI alarm
is displayed on
the active alarm page of the app
or WebUI.
Press the reset button of the
smoke sensor to clear the alarm.
----End
6.3.6.2 Commissioning the Water Sensor
Procedure
Step 1
Set water sensor parameters.
The parameter has been preset before delivery.
In this example, the water sensor is connected to the AI/DI_1 port on the ECC800.
1.
Log in to the ECC800 WebUI as an administrator.
2.
Choose
System Settings
>
Signal Name Modify
. The
Batch Signal Configuration
page is displayed.
3.
Set
Device type
to
ECC800
, set
Device name
to
ECC800
, and click
OK
.
4.
On the query result tab page, set the new signal name of
AI/DI_1
to
Leak
and click
Submit
.
5.
Choose
Monitoring
>
System
>
ECC800
>
Running Parameters
>
AI/DI_1 Port
Settings
.
6.
Set
Leak sensor
to
Enable
and click
Submit
.
7.
Confirm that
Leak sensor type
is automatically identified as
Leak sensor(Rope)
.
Ensure that
Leak power supply
is
Yes
.
Step 2
Check the monitoring functions of water sensor.
Table 6-7
Commissioning the sensor
Check Method
Normal Connection Status
Place the water detection cable
into water.
Leak DI alarm
is displayed on the active alarm page
of the app or WebUI.
----End
6.3.6.3 Commissioning the Temperature Sensor
In the scenario with an emergency fan, perform this operation by default when the
temperature sensor is configured and connected to the AI/DI_2 port.