FusionModule800 Smart Small Data Center
Installation Guide (Six Fans)
6 Power-On Commissioning
Issue 10 (2019-12-20)
Copyright © Huawei Technologies Co., Ltd.
254
Follow-up Procedure
To modify or delete the email parameter settings, click
Confirm
or
Delete
button, the
re-authentication page is displayed. Enter
Login password
and click
Submit
.
6.3.10 Commissioning Cameras and a VCN (Smart ETH Gateway
Networking Scenario)
Figure 6-10
Video system networked over a smart ETH gateway
To ensure the normal operating of the ECC800, avoid high data traffic, such as the
concurrent display of dynamic monitoring of cameras and VCN video playback.
To ensure the normal operating of the ECC800, you can view the videos from a maximum
of two IPC6325-WD-VR cameras concurrently.
6.3.10.1 Commissioning IPC6325 Cameras
Prerequisites
If multiple cameras are accessed, retain the connection of one camera and disconnect
connections from other cameras. After commissioning the connected camera, commission
other cameras in the same way.
Context
The existing network is equipped with the ECC800 that supports the Dynamic Host
Configuration Protocol (DHCP). After the ECC800 and IPC6325 camera are powered on,