3.1 Transportation and Unpacking
3.1.1 Cabinet Transportation and Unpacking
Context
Only trained personnel are allowed to move the cabinet. Remove the packed cabinet
from the pallet using a pallet truck and move the cabinet to the installation position.
To prevent the cabinet from falling over, secure it to the pallet truck using ropes before
moving it.
To prevent shocks or falls, move the cabinet gently. After placing the cabinet in the
installation position, unpack it and take care to prevent scratches. Keep the cabinet
steady during unpacking.
If the cabinet installation environment is in poor condition, to well store the cabinet after
it is unpacked, take measures to prevent dust. You can wrap the cabinet with the original
plastic coat.
Do not tear down the transparent film from the glass door during the installation. The film
will be removed after the entire module is installed.
Procedure
Step 1
Use a pallet truck to transport the cabinet to the installation position.
Step 2
Check that the cabinet package is intact.
Step 3
Cut off and remove the binding straps, and remove the packing.
Step 4
Remove pallets from ordinary cabinets.
Ordinary cabinets include IT cabinets, battery cabinets, and network cabinets.
1.