WARNING:
Before powering up the storage system, a certified electrician must attach all the
power cabling to all the PCMs.
The power cable is connected to the -48V DC PCM with connections to the positive terminal ( ),
negative terminal ( ), and ground terminal ( ).
Verification
16.
Verify that the replacement DC PCM has been successfully installed.
Turn on the PCM and check that the power LED is on.
17.
After the component replacement, initiate
Check Health
on the storage system.
a.
From the Service Console interface, select
Systems
.
b.
Select
Actions
>
Check health
.
18.
If significant time is left in the maintenance window, end the
Maintenance Mode
.
a.
From the Service Console interface, select
Systems
.
b.
Select
Actions
>
Set maintenance mode
.
c.
To end the maintenance window associated with the replacement, click
X
.
The flow of support information and local notifications of system alerts will be sent to Hewlett
Packard Enterprise again.
19.
Follow the return instructions provided with the replacement component.
Replacing the direct-current power cooling module in a controller node
enclosure—SP 5.x
This procedure is for the replacement of an -48V direct-current (DC) power cooling module (PCM) in a
controller node enclosure using HPE 3PAR Service Processor (SP) 5.x.
WARNING:
Since there is a risk of injury from electric shock or high energy levels, only a certified
electrician who knows about the procedures, precautions, and hazards associated with direct-
current (DC) power should perform the power wiring, cabling, routine maintenance, and service of a
storage system installed in a direct-current power environment. Hewlett Packard Enterprise and
partner service personnel are not authorized to perform DC power wiring or cabling.
CAUTION:
Connecting to a direct-current power source outside the designated -48V DC nominal
range (-36V DC to -72V DC) may damage the direct-current power cooling module.
IMPORTANT:
The direct-current components are qualified and supported only with a direct-current
HPE 3PAR StoreServ 8000 Storage system running HPE 3PAR OS 3.3.1 and later versions.
IMPORTANT:
The storage system ordered for installation in a direct-current (DC) power
environment requires the installation of DC-specific components. Use of components with
alternating-current (AC) power in the DC storage system is prohibited.