Figure 5–19: INTERLOCKING BUS PROTECTION SCHEME VIA DIRECT INPUTS/OUTPUTS
In the above application, the following settings should be applied. For UR-series IED 1:
DIRECT OUTPUT DEVICE ID:
“1”
DIRECT I/O CH1 RING CONFIGURATION:
“Yes”
DIRECT I/O CH2 RING CONFIGURATION:
“Yes”
For UR-series IED 2:
DIRECT OUTPUT DEVICE ID:
“2”
DIRECT I/O CH1 RING CONFIGURATION:
“Yes”
DIRECT I/O CH2 RING CONFIGURATION:
“Yes”
For UR-series IED 3:
DIRECT OUTPUT DEVICE ID:
“3”
DIRECT I/O CH1 RING CONFIGURATION:
“Yes”
DIRECT I/O CH2 RING CONFIGURATION:
“Yes”
For UR-series IED 4:
DIRECT OUTPUT DEVICE ID:
“4”
DIRECT I/O CH1 RING CONFIGURATION:
“Yes”
DIRECT I/O CH2 RING CONFIGURATION:
“Yes”
Message delivery time is approximately 0.2 of power system cycle (at 128 kbps) times number of ‘bridges’ between the ori-
gin and destination. Dual-ring configuration effectively reduces the maximum ‘communications distance’ by a factor of two.
In this configuration the following delivery times are expected (at 128 kbps) if both rings are healthy:
IED 1 to IED 2: 0.2 of power system cycle;
IED 1 to IED 3: 0.4 of power system cycle;
IED 1 to IED 4: 0.2 of power system cycle;
IED 2 to IED 3: 0.2 of power system cycle;
IED 2 to IED 4: 0.4 of power system cycle;
IED 3 to IED 4: 0.2 of power system cycle.
If one ring is broken (say TX2-RX2) the delivery times are as follows:
IED 1 to IED 2: 0.2 of power system cycle;
IED 1 to IED 3: 0.4 of power system cycle;
IED 1 to IED 4: 0.6 of power system cycle;
IED 2 to IED 3: 0.2 of power system cycle;
IED 2 to IED 4: 0.4 of power system cycle;
IED 3 to IED 4: 0.2 of power system cycle.
A coordinating timer for this bus protection scheme could be selected to cover the worst case scenario (0.4 of a power sys-
tem cycle). Upon detecting a broken ring, the coordination time should be adaptively increased to 0.6 of a power system
cycle. The complete application requires addressing a number of issues such as failure of both the communications rings,
failure or out-of-service conditions of one of the relays, etc. Self-monitoring flags of the direct inputs and outputs feature
would be primarily used to address these concerns.
842716A1.CDR
UR IED 1
RX1
TX2
TX1
RX2
UR IED 2
TX2
RX2
RX1
TX1
UR IED 4
TX1
RX1
RX2
TX2
UR IED 3
RX2
TX1
TX2
RX1
Содержание G30
Страница 10: ...x G30 Generator Protection System GE Multilin TABLE OF CONTENTS ...
Страница 30: ...1 20 G30 Generator Protection System GE Multilin 1 5 USING THE RELAY 1 GETTING STARTED 1 ...
Страница 414: ...5 274 G30 Generator Protection System GE Multilin 5 10 TESTING 5 SETTINGS 5 ...
Страница 456: ...8 2 G30 Generator Protection System GE Multilin 8 1 DIRECTIONAL PRINCIPLE 8 THEORY OF OPERATION 8 ...
Страница 470: ...9 14 G30 Generator Protection System GE Multilin 9 1 SETTING EXAMPLE 9 APPLICATION OF SETTINGS 9 ...
Страница 484: ...11 12 G30 Generator Protection System GE Multilin 11 6 DISPOSAL 11 MAINTENANCE 11 ...
Страница 512: ...A 28 G30 Generator Protection System GE Multilin A 1 PARAMETER LISTS APPENDIX A A ...
Страница 620: ...B 108 G30 Generator Protection System GE Multilin B 4 MEMORY MAPPING APPENDIX B B ...
Страница 666: ...E 10 G30 Generator Protection System GE Multilin E 1 IEC 60870 5 104 APPENDIX E E ...
Страница 678: ...F 12 G30 Generator Protection System GE Multilin F 2 DNP POINT LISTS APPENDIX F F ...
Страница 687: ...GE Multilin G30 Generator Protection System H 7 APPENDIX H H 2 ABBREVIATIONS H Z Impedance Zone ...