INNOVATION Total 1 Rev 8 06/2013
www.cafection.com
(800) 561-6162
14
INSTALLATION AND SERVICE MANUAL FOR INNOVATION
Total 1
Bean-Cup Brewer
Initial Setup
3.7
Electrical Connection
This equipment must be installed in compliance with applicable Federal, State, Provincial and/or
Local electrical codes having jurisdiction.
Make sure: - The equipment is OFF before plugging it in,
- The equipment has its own electrical outlet and
- NO extension cord is used.
1. Make sure that the power switch at the back of the unit is in the OFF position before plugging it in the
unit;
2. Locate the unit’s 6’ power cord and plug it into its own grounded electrical outlet;
3. Reach to the back of the brewer and toggle the power switch to the ON position. The front lights will
turn on and water will automatically enter the brewer. The fill cycle should take to 2-3 minutes maximum.
4. Once the tank is full, it will take 10-15 minutes to heat the water to brewing temperature;
5. Once the brewing equipment is ready, the selection screen will appear.
The main power switch turns the equipment ON and OFF. This switch should be turned OFF when
servicing any (AC line voltage) electrical components on the equipment.
OFF Position!