10. Commissioning
Commissioning should be performed by a trained WASSP technician immediately after
installation of the system.
The commissioning procedures are designed to be carried out in sequential order. If a test fails,
fix the system until that test can be completed satisfactorily before continuing. Failure to do this
may invalidate the commissioning procedure. Commissioning procedures are divided into two
sets:
1)
Dockside Tests.
2)
Sea Trials.
For all commissioning steps, the WASSP software needs to be running. See “7.4 WASSP
Software Operation” on page 26.
Before these tests are carried out, fill in the
Vessel Identification
on the
General Tab
in
Ship
Setup Options
as this allows data collected on this vessel to be clearly identified for diagnostic
purposes.
Figure 32. General Tab Settings
Fill in the
Transducer
Serial Number