4-24
BA ET18, 20, 24 en* 1.5 * et18_20_24i400.fm
4 Putting into operation
Shatter protection (option)
DANGER
Danger of piercing/penetration by fragments from the front!
Causes serious injury or death.
►
A shatter protection must be installed on a canopy version if an
attachment (for example a hammer) causes fragments to fly around.
This shatter protection takes over the function of a front window. If the
machine is equipped with a cabin, the front window must be closed
during hammer operation.
►
Note restricted work area (see Fig. 96/97)
►
Machine operation is prohibited without a shatter protection.
CAUTION
Accident hazard in conditions of restricted visibility due to rain,
snowfall, dust, etc.
Can cause injury.
►
Stop machine operation immediately.
NOTICE
Only a Wacker Neuson service center may install the shatter protection for
the first time.
NOTICE
Do not use brushes, steel wool or other abrasive cleaners for cleaning the
polycarbonate disk. Do not wipe dust in a dry state.
Information
The shatter protection (canopy option) protects the user against fragments
from the front.
►
The machine owner must ensure that the hazard situation is evaluated
and that the national regulations are observed.
►
The machine owner must ensure that only work is performed that does
not require any higher protection.
►
Accidents cannot be fully avoided despite equipping a machine with
protective structures.
The shatter protection cannot be combined with a protective Front Guard
structure.
Summary of Contents for ET12 02
Page 8: ...EG 4 BA ET18 20 24 en 1 5 et18_20_24konf fm Declaration of conformity Notes...
Page 16: ...1 8 BA ET18 20 24 en 1 5 et18_20_24v100 fm 1 Foreword Notes...
Page 48: ...3 12 BA ET18 20 24 en 1 5 et18_20_24e300 fm 3 Introduction Warning labels Cabin Canopy...
Page 53: ...BA ET18 20 24 en 1 5 et18_20_24e300 fm 3 17 Introduction 3 Information labels...
Page 60: ...3 24 BA ET18 20 24 en 1 5 et18_20_24e300 fm 3 Introduction...
Page 104: ...4 44 BA ET18 20 24 en 1 5 et18_20_24i400 fm 4 Putting into operation...
Page 118: ...5 14 BA ET18 20 24 en 1 5 et18_20_24b510 fm 5 Operation...
Page 170: ...5 66 BA ET18 20 24 en 1 5 et18_20_24b510 fm 5 Operation Notes...
Page 178: ...6 8 BA ET18 20 24 en 1 5 et18_20_24t600 fm 6 Transport...
Page 230: ...7 52 BA ET18 20 24 en 1 5 et18_20_24w710 fm 7 Maintenance Notes...
Page 280: ...9 48 BA ET18 20 24 en 1 5 et18_20_24t900 fm 9 Technical data Notes...