5-8
BA ET18, 20, 24 en* 1.5 * et18_20_24b500.fm
5 Operation
Parking the machine
WARNING
Accident hazard if machine tips over or rolls away after parking it!
Can cause serious injury or death.
►
Lower the boom and the stabilizer blade to the ground.
►
Secure the machine accordingly (for example with chocks).
1. Park the vehicle on firm, level, and horizontal ground.
2. Position the boom straight ahead at the center of the machine.
3. Lower the boom and the stabilizer blade to the ground.
4. Stop the engine.
5. Operate the control lever repeatedly to release the pressure in the
hydraulic system.
6. Remove the starting key and carry it with you.
7. Raise the control lever base.
8. Close the windows and doors.
9. Close and lock all covers and doors.
10.Secure the tracks accordingly (for example with chocks, blocks) as
shown in
Information
Fill up the tank with the correct fuel type at the end of each working day to
prevent the formation of condensation water in the fuel tank. Do not fill the
tank completey so the fuel can expand.
Parking the machine on slopes
If parking the machine on a slope cannot be avoided, observe the
following in addition:
• Position the boom on the downhill side of the machine and firmly press
the attachment into the ground.
• Press the stabilizer blade against the ground.
• Secure the tracks accordingly (for example with chocks, blocks) as
shown in
Fig. 124Parking the machine
Fig. 125Parking the machine on slopes
Summary of Contents for ET12 02
Page 8: ...EG 4 BA ET18 20 24 en 1 5 et18_20_24konf fm Declaration of conformity Notes...
Page 16: ...1 8 BA ET18 20 24 en 1 5 et18_20_24v100 fm 1 Foreword Notes...
Page 48: ...3 12 BA ET18 20 24 en 1 5 et18_20_24e300 fm 3 Introduction Warning labels Cabin Canopy...
Page 53: ...BA ET18 20 24 en 1 5 et18_20_24e300 fm 3 17 Introduction 3 Information labels...
Page 60: ...3 24 BA ET18 20 24 en 1 5 et18_20_24e300 fm 3 Introduction...
Page 104: ...4 44 BA ET18 20 24 en 1 5 et18_20_24i400 fm 4 Putting into operation...
Page 118: ...5 14 BA ET18 20 24 en 1 5 et18_20_24b510 fm 5 Operation...
Page 170: ...5 66 BA ET18 20 24 en 1 5 et18_20_24b510 fm 5 Operation Notes...
Page 178: ...6 8 BA ET18 20 24 en 1 5 et18_20_24t600 fm 6 Transport...
Page 230: ...7 52 BA ET18 20 24 en 1 5 et18_20_24w710 fm 7 Maintenance Notes...
Page 280: ...9 48 BA ET18 20 24 en 1 5 et18_20_24t900 fm 9 Technical data Notes...