15
Siting
Minimum clearances
1500
1200
1200
1500
Foundations
Site the heat pump horizontally on a per-
manently solid surface. We recommend
laying concrete foundations as shown in
the following diagrams.
■ Provide an adequately sized
recess (see diagram below) in the
foundations to permit the lines (heat-
ing water flow and return, cables and
condensate drain) to be brought into
the heat pump from below.
■ Design the foundations, supporting
surface and cable ducts so that small
animals cannot get into the heat pump
or cable ducts.
■ Drain all condensate derived from the
air (subject to temperature and relative
humidity up to 20 l/h) via a DN 40 drain
pipe, which should be protected from
frost and provide a steady fall.
If possible connect the condensate
drain to a drainage or sewer system.
In this case, provide a siphon with a
backup level of at least 60 mm in the
frost-protected area.
Where the ground is able to absorb
water, the condensate can be soaked
away down to a frost-free depth into a
gravel bed.
■ Where appropriate, provide thermal
insulation or a ribbon heater around
the condensate drain hose on site.
Technical guide
Weight
(with silencer hoods): 309 kg
Preparing for installation
External heat pump type AWO-M-AC 301.A
(cont.)
5692 875 GB
Installation
Summary of Contents for Vitocal 300 AWO-M-AC 301.A
Page 5: ...5 Certificates Declaration of conformity 148 Keyword index 149 Index Index cont 5692 875 GB...
Page 47: ...47 Installation sequence Removing the transport brackets cont 5692 875 GB Installation...
Page 52: ...52 3x 3x 3x 3x 9 8 Installation sequence Fitting the outer panels cont 5692 875 GB...
Page 53: ...53 3x 10 3x 2x 11 Installation sequence Fitting the outer panels cont 5692 875 GB Installation...
Page 104: ...104 Fitting the front panel 1 2 2 Installation sequence Closing the heat pump cont 5692 875 GB...
Page 128: ...128 051 052 008 066 038 063 064 Parts lists Parts list type AWCI M AC 301 A cont 5692 875 GB...