A-5
Installation Information
5.
Connect the blue AC power wire to the center screw on the AC power terminal
block.
6.
Connect the brown AC power wire to the right screw on the AC power
terminal block.
7.
If this is the +5 volt supply in a non-redundant power system or the lower +5 volt
supply in a redundant power system, perform the following steps:
a.
Place the two heavy black cables from the Signal Processor frame or the
upper power supply on the LEFT stud.
b. Place the two heavy red cables from the Signal Processor frame or the
upper power supply on the RIGHT stud.
WARNING
Note that the connections on the Jeta +5 Volt supply, referenced in Step 7, are
just the opposite of the connections that you removed from the Todd +5 Volt
supply. Note also that the studs, nuts, and cable ends for the positive (red)
cables are larger than those for the negative (black) cables, to prevent them
from being incorrectly connected. Connecting the cables incorrectly could
destroy portions of your power supply and/or switcher.
c.
Install the lockwashers and nuts and torque to 80 inch pounds.
WARNING
Use caution when tightening the nuts. Insufficient torquing of the nuts may
cause overheating of the terminals which could result in fire. However,
excessive torquing of the nuts may break the studs.
NOTE:
Refer to
Summary of Contents for Grass Valley 4000
Page 3: ...iii Tektronix Grass Valley Products P O Box 1114 Grass Valley CA 95945 916 478 3800 ...
Page 4: ...iv Tektronix Grass Valley Products P O Box 1114 Grass Valley CA 95945 916 478 3800 ...
Page 34: ...1 20 Section 1 System Overview ...
Page 138: ...2 104 Section 2 Installation ...
Page 196: ...3 58 Section 3 Functional Description ...
Page 286: ...Index 6 Index ...