REFUdrive 500 RD51
Start-up
6-1
DOK-RD500*-RD51*******-IB01-EN-P
6 Start-up
6.1
Steps to prepare for commissioning
The power terminals should be connected-up, as specified in Section 3.4,
and the control terminals, as specified in Section 3.7 .
Check whether the star/delta jumpes have been correctly connected at
the motor terminal board.
Observe the “Hazardous voltage warning information” in Section 3.2!
It should also be ensured, that signal-, line supply- and motor feeder
cables have been separately routed with a minimum clearance between
them. The setpoint cables must be shielded. Please refer to Section 3.1
“EMC-correct design of drives”.
Before first commissioning the electrical system, the qualified electrician
or engineer should first check whether the equipment corresponds, both
electrically and mechanically to the safety requirements
(5 Paragraph 1 No. 1 VBG 4), specified by
•
- the accident prevention regulations, and
•
- the general electrical regulations.
Check whether a rotating motor could cause human injury or material
damage!
The power- and control voltages can be powered-up after all of the
control-, setpoint and power supply cables have been connected. The
operator panel displays ”Switch-on enable” message after approx. 10 sec
6.2
Procedure when first commissioning
The factory setting is always assumed regarding the parameterization in
this “commissioning” section.
The following diagram guides you through the simplest start-up via the
Quick Setup and starting the drive with the factory settings.
The second route represents, as example, several settings per “Prompted
parameterization”. Please refer to Section 5 in this Instruction Manual for
all other possibilities of parameterizing the drive.
The factory settings of the parameterization are also provided in Section 5
in the tables.