Reading from stick: Starts reading the data from the stick. This operation
is only possible with READ sticks. The data of the set data set is copied
to the LMS control. First a check is carried out as to whether the data
set may be imported. If the data set is incompatible, it must not be im
ported. The display resets toNo operation and displays an error mes
sage. The textReading from stick remains until the operation is comple
ted or an error occurs. As soon as data transmission begins, the LMS
control goes in a parameterization position. As soon as parameters are
transferred, the LMS control must be unlocked transmission has ended.
Fault 183 parameterization is displayed.
Writing on stick: Starts writing the data from the LMS control to the stick.
This operation is only possible with WRITE sticks. The data is written in
to the previously set data set. Before writing of the data begins, it is
checked whether the stick has sufficient capacity for the data and that
the respective customer number is correct. The textWriting on stick re
mains until the operation is completed or a fault occurs.
PStick progress (7253)
The read or write progress is displayed as a percentage. If no operation is
active or a fault occurs, 0% is displayed.
9.2.21 Configuration of extension modules
Function extension module 1 (7300), Function extension
module 2 (7375) und Function extension module 3 (7450)
When a function is selected, the inputs and outputs are occupied on the
extension module with the functions according to the following table:
Connection ter
minal on module
QX21 QX22 QX23 BX2
1
BX2
2
H2/H21 H22
Multi-functional
*
*
*
*
*
*
*
Heating circuit 1
Y1
Y2
Q2
B1
*
*
*
Heating circuit 2
Y5
Y6
Q6
B12
*
*
*
Heating circuit 3
Y11
Y12
Q20
B14
*
*
*
Return sensor
Y7
Y8
Q1
B7
*
*
*
Solar DHW
*
*
Q5
B6
B31
*
*
Primary control/
system pump
Y19
Y20
Q14
B15
*
*
*
* Freely selectable in QX.../ BX...
FS = DHW flow switch; AVS75.390 = H2; AVS75.370 = H21
Tab.14 Legend
Q1
Boiler pump
Q2
1. Heating circuit pump
Q5
Collector pump
Q6
2. Heating circuit pump
Q14
System pump
Q20
Heating circuit pump HC3
Y1
1. Heating circuit mixer OPEN
Y2
1. Heating circuit mixer CLOSED
Y5
2. Heating circuit mixer OPEN
Y6
2. Heating circuit mixer CLOSED
Y7
Return maintenance valve OPEN
Y8
Return maintenance valve CLOSED
Y11
3. Heating circuit mixer OPEN
9 Settings
7636047 - 02 - 24082015
119
Summary of Contents for eurocondense four 125 kw
Page 19: ...3 2 6 Wiring diagram Fig 3 Wiring diagram 3 Technical specifications 7636047 02 24082015 19 ...
Page 40: ...Fig 22 Legend for application examples part 2 5 Before installation 40 7636047 02 24082015 ...
Page 143: ...13 Appendix 13 1 Declaration of conformity 13 Appendix 7636047 02 24082015 143 ...
Page 146: ...Index 146 7636047 02 24082015 ...
Page 148: ...7636047 02 24082015 ...