![NR Electric PCS-9611 Instruction Manual Download Page 111](http://html1.mh-extra.com/html/nr-electric/pcs-9611/pcs-9611_instruction-manual_1713962111.webp)
4 Supervision
PCS-9611 Feeder Relay
4-3
Date: 2014-04-08
protection VT is in abnormal status.
(1) The negative phase sequence voltage is greater than 8V.
(2) The positive phase sequence voltage is less than 30V, and any of the phase currents is
greater than 0.04In.
Then the alarm signals [Alm_Device] and [VTS.Alm] are issued 10s later, and the LED
“
ALARM
” will be on at the same time. When the protection VT status returns to normal
condition, the alarm will restore automatically 1.25s later. In case the protection VT circuit is
failed, these protective elements dependent on voltage will be blocked.
If the fast VT failure is detected, the internal signal
“VTS.InstAlm” will be “1” without any time
delay. In the fast VTS element, the phase current or the negative sequence current must be
taken into account.
The logic diagram of the protection VTS element is shown as below.
VTS.InstAlm
&
&
&
[VTS.Alm]
U
1
< 30V
U
2
> 8V
Ic < [VTS.I_Set]
Ib < [VTS.I_Set]
Ia < [VTS.I_Set]
I
2
< [VTS.I2_Set]
[VTS.En]
[Sig_MCB_VT]
&
&
Prot.OnLoad
&
U
1
< 15V
10s
0
[
BI_En_VT
]
&
Figure 4.2-2 Logic diagram of the protection VTS element
Where:
“Prot.OnLoad” is the signal for denoting the system is on load state;
[VTS.En] is the logic setting of the protection VTS function;
[VTS.I_Set] is the phase current setting of the protection VTS function;
[VTS.I2_Set] is the negative sequence current setting of the protection VTS function;
[Sig_MCB_VT] is the VT supervision input from VT
’s miniature circuit breaker (MCB)
auxiliary contact which shows the MCB whether is opened;
[BI_En_VT] is the binary input for denoting the local VT is in service;
“U
1
” is the positive sequence voltage;
“U
2
” is the negative sequence voltage.
Synchro-check VT supervision
This function is used to supervise the synchro-check voltage transformer circuit. When the
Summary of Contents for PCS-9611
Page 1: ...PCS 9611 Feeder Relay Instruction Manual NR Electric Co Ltd...
Page 2: ......
Page 10: ...1 Introduction PCS 9611 Feeder Relay 1 b Date 2014 04 08...
Page 30: ...2 Technical Data PCS 9611 Feeder Relay 2 14 Date 2014 04 08...
Page 36: ...3 Operation Theory PCS 9611 Feeder Relay 3 f Date 2014 04 08...
Page 108: ...4 Supervision PCS 9611 Feeder Relay 4 b Date 2014 04 08...
Page 116: ...5 Management Function PCS 9611 Feeder Relay 5 b Date 2014 04 08...
Page 120: ...5 Management Function PCS 9611 Feeder Relay 5 4 Date 2014 04 08...
Page 218: ...9 Configurable Function PCS 9611 Feeder Relay 9 b Date 2014 04 08...
Page 232: ...9 Configurable Function PCS 9611 Feeder Relay 9 14 Date 2014 04 08...
Page 262: ...11 Installation PCS 9611 Feeder Relay 11 b Date 2014 04 08...
Page 272: ...12 Commissioning PCS 9611 Feeder Relay 12 b Date 2014 04 08...
Page 292: ...13 Maintenance PCS 9611 Feeder Relay 13 b Date 2014 04 08...
Page 296: ...14 Decommissioning and Disposal PCS 9611 Feeder Relay 14 b Date 2014 04 08...
Page 298: ...14 Decommissioning and Disposal PCS 9611 Feeder Relay 14 2 Date 2014 04 08...
Page 300: ...15 Manual Version History PCS 9611 Feeder Relay 15 2 Date 2014 04 08...