5-35
5.3.3.3 Leak Test of the System Switch Assembly
Perform a leak test of the system switch assembly by using the following tools:
Negative pressure ball (quantity:1)
3106-06-00 adapter connector (quantity:1)
3126-06-00 tube plug (quantity:2)
PU tube (6X100) (quantity:1)
Test procedures:
1. Turn off the pipeline gas supplies and turn on the system switch. Bleed the residual
pressure by turning on the flow regulators.
2. Turn off the system switch.
3. Pull out No.45 or 51 PU tube (No.45 tube in case of O2+N2O configuration, No.45
and 51 tubes in case of O2+AIR configuration, and No.45 tube in case of single O2
configuration) which connects the system switch assembly to the flow regulator. The
end of the tube which connects the system switch assembly is not pulled out but the
other end is.
4. Pull out No.43 or 50 PU tube (No.43 tube in case of O2+N2O configuration, No.43
and 50 tubes in case of O2+AIR configuration, and No.43 tube in case of single O2
configuration) which connects the pipeline gas supply inlet assembly to the system
switch assembly. The end of the tube which connects the system switch assembly is
pulled out but the other end is not.
5. Flatten the negative pressure ball to remove the gas inside. Then re-install the gas
outlet switch of the negative pressure ball properly. Connect the other end of the
negative pressure ball to the pulled-out end of No.45 or 51 PU tube in turn through
3106-06-00 adapter connector, as shown below.
Summary of Contents for WATO EX-55
Page 1: ...WATO EX 55 65 Anesthesia Machine Service Manual ...
Page 2: ......
Page 4: ...II FOR YOUR NOTES ...
Page 6: ...IV FOR YOUR NOTES ...
Page 12: ...6 FOR YOUR NOTES ...
Page 58: ...3 22 FOR YOUR NOTES ...
Page 242: ...6 54 6 4 1 Electrical Connections Electrical Circuit Diagram ...
Page 260: ...6 72 FOR YOUR NOTES ...
Page 261: ...7 1 7 Parts 7 1 Main Unit 7 1 1 Main Unit 7 1 1 1 Exploded View ...
Page 321: ......
Page 322: ...P N 0621 20 78654 1 1 ...