19.2 Road Setting-out
It is possible to perform alignment setting-out for the designated point by using the chainage and offset which is
ensured in road design.
For and alignment setout a horizontal alignment must have been uploaded (Refer to 19.1.5 Reiceiving alignment)
or entered manully (Refer to 19.1.1 Define alignment).
The vertical alignment is optional, but is required to compute cut and fill.
Rule
:
Offset left: the horizontal distance from the left stake point to the center line.
Offset right: the horizontal distance from the right stake point to the center line.
Elevation difference: Left (right) is the elevation difference between left (right) stake and the center line point.