FusionModule5000 Smart Modular Data Center
Commissioning Guide
3 Preparations for Power-On Commissioning
Issue 06 (2020-03-20)
Copyright © Huawei Technologies Co., Ltd.
20
Check Item
Operation
Expected Result
connections
signal cables.
Check the communications
cable connection to the
ECC800.
requirements.
Smart cooling
product pipe
connections
Check the pipe connections to
air cooled smart cooling
products.
The pipes are properly installed,
and the thermal insulation layers
are intact.