Category
Required Materials
Operation
reserved port using conversion adapters at
both ends.
Figure 4-26
Connecting water inlet and outlet pipes
(1) Reserved port (1 inch, BSPT,
external threaded connector)
(2) Pagoda connector
(DN25, standard
configuration, delivered
with the product)
(3) Clamp (standard
configuration, delivered
with the product)
(4) Rubber hose (DN25
recommended, to be purchased)
(5) Conversion adapter (1
inch, BSPP, the inner
screw thread joint, to be
purchased)
(6) Rigid PPR or
aluminum-plastic pipe
(DN32 recommended, to
be purchased)
(7) Stainless corrugated hose (1
inch, BSPP, internal threaded
connector, DN25 recommended,
length 200 mm recommended, to
be purchased)
(8) Steel pipe (DN25,
recommended, to be
purchased)