FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
9 Installing Monitoring Devices
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
115
Step 4
Connect the server power cables to the PDU2000.
The server uses dual power supplies. Connect the two power cables to different PDU2000s.
Figure 9-5
Connecting power cables for the server
----End
9.3 (Optional) Installing a VCN500
Procedure
Step 1
Determine the mounting holes for the VCN500 based on the network cabinet device layout,
adjust the guide rails, and install floating nuts.
Step 2
Place the VCN500 into the network cabinet with caution, and gently press down buttons on
the mounting ears, as shown in