FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
9 Installing Monitoring Devices
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
146
Figure 9-48
Connecting power connector cables (BOM number: 14190892)
Figure 9-49
Connecting power connector cables (BOM number: 14190242)
Step 3
Secure the pad power connector holder, as shown in
1.
Remove the baffle plate from the power connector mounting holes in the door box.
2.
Secure the pad power connector holder to the door box using two M4x12 screw
assemblies.
Figure 9-50
Securing the pad power connector holder
(1) Door box