Procedure
Step 1
Install floating nuts.
Step 2
Secure a side plate to the cabinet using four M6 screws and the floating nuts.
Step 3
Install other side plates in the same way.
Figure 4-38
Installing a cabinet side plate
----End
Follow-up Procedure
After adjusting side plates, remove the labels on the plates.
4.6 (Optional) Adjusting Battery Cabinet Side Plates
If an auxiliary battery cabinet (no circuit breaker) is deployed in the smart module, remove
the plate on one side of the main battery cabinet and install the side plate on the outer side of
the auxiliary cabinet based on the label on the main battery cabinet. Ensure that there are side
plates on the outer sides of the main and auxiliary battery cabinets and there is no side plate
between the adjacent battery cabinets.
After adjusting the side plate of the battery cabinet, remove the label which indicates side plate
adjustment from the main battery cabinet.