FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
A Appendix
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
201
Figure A-3
Installing a floating nut
A.4 Preparing a Monitoring Cable
Prerequisites
A network cable, cord end terminals, and RJ45 connectors are prepared.
The following tools are prepared:
−
Wire stripper
−
Crimping tool
−
RJ45 crimping tool
−
Electrician's knife
−
Insulation tape
Preparing a Cord End Terminal
shows how to prepare a cord end terminal.
1.
Strip the insulation layer of cable B to expose cable core C.
2.
Put cable core C through cord end terminal A.
3.
Crimp the metal part of cord end terminal A using the crimping tool.