FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
12 Cable Routing
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
190
Figure 12-29
Incorrect battery cable connection method
Connecting Cables to the Circuit Breaker in a Battery Cabinet
Before connecting cables, ensure that the circuit breaker is OFF.
Connect cables to the circuit breaker as follows:
1.
(Optional) If the intelligent battery monitoring system is deployed, knock off the cover
on the CIM indicator hole on the circuit breaker panel, as shown by (1) in
2.
Remove the circuit breaker panel, as shown by (2) in
3.
Connect the battery cables
+
,
N
, and
-
, as shown by (3) in
4.
Connect the UPS cables
+
,
N
, and
-
, as shown by (4) in
5.
(Optional) If two battery strings are deployed, connect the UPS terminals
+
,
N
, and
-
for
one battery string to the UPS terminals
+
,
N
, and
-
for the other battery string.